Tirupati starts producing flake graphite at Sahamamy

CBCIE Time:Feb 21, 2023 16:09 Source:miningweekly

London-listed Tirupati Graphite has started producing flake graphite at its Sahamamy project, in Madagascar, at a mining rate of 450 000 t/y and a final production rate of 18 000 t/y.

The commissioning of the new facilities was delayed by three months owing to shipping delays and weather-related interruptions in the country caused by Cyclone Cheneso, which hit Madagascar in mid-January.

The company has advised that, since commissioning the new facilities, the head grade feed into the 400 000 t/y preconcentrate plant has been in the target range of 4% to 5%, with a target product grade of more than 95% having been achieved consistently.

Tirupati advises that there have been no significant challenges in the startup of the new facilities and the operations are expected to reach the minimum stable output of 80% of nameplate capacity by March.

The company expects the Sahamamy project to produce between 800 t and 1 000 t in the quarter ending March 31, and between 3 500 t and 3 700 t of flake graphite in the quarter ending June 30.

Meanwhile, Tirupati says a second preconcentrate unit at the Vatomina project, in Madagascar, has been operating seamlessly since its commissioning late in December.

The company has made progress in improving the average head grade at Vatomina by using the extension deposits of currently operating pits. Tirupati envisions improving the head grade to an average of more than 3.5% at the project, from the current 2.5% range, as well as nameplate production capacity of 12 000 t/y of flake graphite.

Tirupati expects the Vatomina project to produce between 1 700 t and 1 900 t in the quarter ending March 31, and between 2 600 t and 2 800 t in the quarter ending June 30.

Chairperson Shishir Poddar says the demand for graphite globally is overwhelmingly positive, owing to it being a key component in electric vehicle batteries. With more than ten-million of these vehicles having been sold in 2022, the demand and price for graphite is set to remain strong for the foreseeable future.

WEATHERING THE STORM

Tirupati says it strengthened its infrastructure late in 2022 already, in preparation for the rainy season, which ensured that there was minimal damage from the recent severe weather.

When the cyclone hit Madagascar in January, Tirupati temporarily scaled back operations at both the Sahamamy and Vatomina projects for ten days to ensure the safety of its personnel and assets.

The company confirms there have been no injuries to staff or damage to property, and operations have since been scaled up to normal as water levels receded.

Tirupati affirms it remains prepared to mitigate the effects of any further adverse weather conditions. 

All articles, pictures, reports and other original works on the website that are attributed to CBCIE are non-public information, only for members. No one may reproduce or otherwise use the original content of this website without our permission. If you need to use it, please call
+86 18135172048 to apply for authorisation. CBCIE reserves the right to pursue any infringement and citation contrary to the original intent.

Disclaimer:CBCIE is committed to building a comprehensive and authoritative metal information platform, and strives to provide a full range of data and information services and decision-making support for metal industry researchers and practitioners. However, the information on this website is for reference only and is not intended as direct advice for investors' decision-making. Any investment, purchase, sale or operation based on the information on this website should be at your own risk and is not related to CBCIE.

Contact us

Contact us for more CBC information and services.

Get in touch
CBC专家咨询 关闭
close
WeCom

CS Manager:
Zizhen Zhang

+86 18135172048